Phase 1 Membrane Project, Day 80 (December 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Last given completion date: December 18, 2025)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, rain

No work onsite today.

NOTE: I believe Prostar is waiting for some updated design work from Strata Engineering before continuing, which means we may not see anyone on site, except possibly for inspections, until Monday, December 8th.

Phase 1 Membrane Project, Day 79 (December 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Last given completion date: December 18, 2025)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mix of clouds and showers

Work done today:

  • Additional work on the membrane between the 244 and 248 buildings
  • Workers onsite: Observed at least 1

Phase 1 Membrane Project, Day 78 (December 2, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Last given completion date: December 18, 2025)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, mix of sun and cloud

No work onsite today.

Prostar is apparently awaiting a Field Report from Strata Engineering to resume specific work. The patios are estimated to be 95% complete at this stage.

Phase 1 Membrane Project, Day 77 (December 1, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Last given completion date: December 18, 2025)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, clouds and intermittent showers in the afternoon

The biweekly onsite meeting took place with:

  • Strata Engineering
  • Prostar
  • Copperstone Council, represented by the Vice President
  • Quay Pacific had no representation (no reason given)

Prostar updated on plans moving forward:

  • They hope to have the patios finished before the Christmas break.
  • They hope to have some soil put back before the Christmas break.
  • Work will continue until December 22, then resume on January 2, 2026.

Work done today:

  • More work on completing installation of membrane on the five affected patios.
  • Workers onsite: At least four.

Phase 1 Membrane Project, Day 76 (November 29, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Last given completion date: December 18, 2025)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, overcast

Of the five Saturdays in November, this is the only one when work was performed onsite.

Work done today:

  • Membrane applied to concrete lip along affected patios.
  • Membrane extended along the base of the 244 and 248 buildings and pillars.
  • Workers onsite: At least 4.

Phase 1 Membrane Project, Day 75 (November 28, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Last given completion date: December 18, 2025)
Primary contractor: Prostar https://prostar.ca/

Weather: Clear, 9C

Work done today:

  • Membrane applied to the concrete slab behind the 244 building.
  • Membrane applied to the lower area of the concrete slab between the 244 and 248 buildings, adjacent to the parking lot.
  • Work to prepare for membrane to be extended up the base of the 244 and 248 buildings and pillars. This consisted of placing protective board, then affixing them in place with industrial nails/washers.
  • Workers onsite: At least 4.