Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
An UNOFFICIAL site for Copperstone, New Westminster
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
This problem seems to have begun when the garbage contractor pushed the left dumpster back into the garbage room with the lids down. The ceiling of the garbage room is too low to allow the lids to be completely folded back, as should have been (and is normally) done.
The lids were propped open with rods, but this only gives limited clearance. This led to several issues:
I used a combo of dustbin, picker, broom and work gloves to:
I am not on council, but in my opinion, the following needs to happen:
So, how was your Sunday? 😛
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
It’s the end of the second week of the project and as far as I can tell, there has been no update from Strata Engineering, Prostar, Quay Pacific or Copperstone Council on why nothing is happening.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.
Phase 1 Membrane Replacement Project
Start Date: August 11, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
No activity onsite today.