Phase 1 Membrane Project, Day 28 (October 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done:

  • Completed removal of membrane from all patios that are part of Phase 1 (five total)
  • Tested equipment and did partial removal of membrane in open area
  • Workers onsite: At least three

Phase 1 Membrane Project, Day 29 (October 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

No work onsite today.

NOTE: Currently work is not being done on Saturdays, though under city permit, it is allowed. I am including Saturdays to avoid confusion about what is happening on those days.

Phase 1 Membrane Project, Day 27 (October 2, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done (first work since September 19th):

  • First three patios had membrane removed
  • Partial removal of membrane in area between 244 and 248 buildings
  • Workers onsite: Observed 3, possibly more