See the Prostar notice below.
The notice did not cover a few important areas, such as mail and deliveries and pedestrian access. I will update this post as more information is made available.
See the Prostar notice below.
The notice did not cover a few important areas, such as mail and deliveries and pedestrian access. I will update this post as more information is made available.
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 26°C, sunny with high cloud
Workers onsite: At least two
Work done today:

Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 26°C, sunny
Workers onsite: At least two
Work done today:



Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 25°C, sunny, high haze
Workers onsite: None
No work onsite today. 🤡
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 25°C, sunny
Workers onsite: None
No work onsite today.
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 25°C, sunny
Workers onsite: None
No work onsite today.