Membrane work, June 20, 2026

Weather: 23°C, sunny
Workers onsite: At least 4

Work done today:

  • Work today was focused on restoring pavers on patios in the emergency area. This work is nearly complete.

Membrane work, June 19, 2026

Weather: 26°C, sunny
Workers onsite: At least 4-6

Work done today:

  • Sidewalk pavers re-instated in emergency repair area.
  • Many of the pavers on patios in the emergency area have been re-instated, with pedestals being used in place of what were previously wooden beams.
  • Some initial re-instatement of the parking lot pavers along the sidewalk in the Phase 1 extension.

Membrane work, June 18, 2026

Weather: 27°C, sunny
Workers onsite: At least 6

Work done today:

  • Sand and soil are being placed in the emergency repair area.
  • Some patio pavers have been put back in place in the same area.

Membrane work, June 17, 2026

Weather: 24°C, sunny
Workers onsite: At least 7

Work done today:

  • Compacting of sand in the Phase 1 extension area.
  • Continued restoration of sidewalk pavers in Phase 1 area.
  • Start of full re-instatement of planter adjacent to the 248 building.
  • Cutting and placement of more wooden beams in the emergency repair area.

You can help water the Heritage Courtyard trees

Owners and tenants are invited to help water the trees in the Heritage Courtyard.

Two hoses have been placed and each is equipped with a hand-operated nozzle. This means you must actively engage the nozzle for the water to come out–this is a requirement of the Stage 3 Water Restrictions which came into effect on June 8 throughout Metro Vancouver.

If you water the trees, thank you! Please coil and put the hoses back when you’re done. There’s no need to turn the water off or on, as the nozzles will insure the water does not leak out.

Membrane work, June 16, 2026

Weather: 24°C, sunny
Workers onsite: At least 4-6

Work done today:

  • Blue Drop installed irrigation piping in the emergency repair area.
  • Additional work on the emergency repair area to install aeration mat and placement of wooden beams.
  • Sidewalk from staircase and Allan blocks both extended in the Phase 1 extension.
  • Wooden beams placed in Phase 1 extension.