Membrane work, July 10, 2026

Weather: 23°C, cloudy, some sun
Workers onsite: At least five

Work done today:

  • Pavers were extended out from the main entrance of the 244 building main entrance
  • This allows use of both the main entrance and the fire door exit adjacent to it

Membrane work, July 9, 2026

Weather: 22°C, sun and clouds
Workers onsite: At least four

Work done today:

  • Sand compacted in front of 244 main entrance
  • Pavers restored in front of the 244 main entrance
  • Partial removal of sidewalk/pavers from adjacent fire door to allow for completion of work in area
  • Pedestrian access restored through main entrance via temporary “bridge” (see photos below)

Mail was delivered today after I again let in the postal worker, but with the main entrance open, deliveries, and guests will now be able to get in and out of the building as they normally would.

The work was actually completed a day earlier than anticipated, per the official Prostar notice.

There is no timeline yet on completion of the Phase 1 extension area, but I believe council has decisions to make regarding sloping and drains, which should happen soon.

Building 244 pedestrian access to entrance restored by Friday, July 10, 2026

UPDATE, 7 pm, July 9, 2026: Work was actually completed a day early, access to the 244 main entrance is now open.

As the title states, Prostar has released the following notice stating the Building 244 main entrance will be open again to pedestrian access by tomorrow, July 10, 2026:

Membrane work, July 8, 2026

Weather: 23°C, mostly cloudy, sun late
Workers onsite: At least four

Work done today:

  • Sealant applied to the area in the Building 244 entrance area
  • Membrane applied to the area in Building 244 entrance area

I also let the letter carrier in for the third day in a row. Apologies if she only brought you bills!