Phase 1 Membrane Project, Day 133 (February 13, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, rain and clouds

Work done today:

  • The excess fabric was trimmed along the top edge of the concrete curb at the base of the retaining wall behind the 244 building.
  • The area in the first tier of the retaining wall to the right of the ventilation shaft was tidied up and soil was used to fill the space. The soil was taken from further down the first tier.
  • It appears the exposed electrical cable on the pavers was placed under the pavers.
  • Soil was also taken from the pile at the front of the site, but I could not determine where it went.
  • Workers onsite: Two.

I believe the spout in the photo above is the one seen in this photo I took yesterday, just visible near the small flag near the centre of the photo:

Phase 1 Membrane Project, Day 132 (February 12, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, cloudy

No work onsite today.

I decided to take a walk along the newly-reopened path leading to the stairs and found a few things that stood out–not in a good way.

Phase 1 Membrane Project, Day 131 (February 11, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, mostly sunny, some clouds

No work onsite today.

Fun Fact: Today marks six months since mobilization began on the membrane project, which started on August 11, 2025.

Phase 1 Membrane Project, Day 130 (February 10, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, mostly sunny

No work onsite today.

Cleaning the Allen Street staircase

Council Vice President Jeff has finished power-washing the stairs and walk leading to Allen Street, on the south side of the 244 building.

You can see how much dirt had built up over the years in this in-progress shot of the work:

And the same wall after cleaning was complete:

I don’t have a before shot of the stairs, but here’s how they looked after cleaning:

(Jeff does the power-washing on his own time and at his own expense, so it doesn’t take away from his duties as a member of Copperstone Council.)

Phase 1 Membrane Project, Day 129 (February 9, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, showers

No work onsite today.

The biweekly meeting was held onsite today with representatives from:

  • Prostar
  • Strata Engineering
  • Quay Pacific
  • Copperstone Council (represented by the Vice President)