Phase 2 membrane project, Day 19–August 11, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Work done today:

  • Pavers put back or partially restored on four patios
  • Membrane completed on four of the five Building 240 patios
  • Initial clearing of the last area on the south side of the parking lot, to allow for removal of old membrane

Phase 2 membrane project, Day 18–August 10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 25°C, sunny
Workers onsite: At least two

Work done today:

  • Additional work on patios by the 240 and 244 buildings

Phase 2 membrane project, Day 17–August 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 25°C, sunny
Workers onsite: At least two

Work done today:

  • Additional work on the patios around the 240 and 244 buildings

Temporary walkway closure–August 5, 6 or 7th, 2026–you pick!

This notice was released by Prostar today:

  • Actual closure started on August 5
  • Notice to owners sent August 7, but dated August 6

Speaking of updates, Prostar has had people onsite and working since May 4, 2026. Here is an update on what has been finished in that 3+ month period:

  • The Phase 1 extension is incomplete
  • The emergency area is incomplete
  • The Stage 3 area is incomplete
  • The patios are incomplete

Bonus:

  • The partial restoration of pavers in front of Building 244 is so out of alignment you get this:

Phase 2 membrane project, Day 16–August 7, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 28°C, sunny
Workers onsite: At least three

Work done today:

  • Two of the Building 240 patios had membrane applied
  • Sealant was applied to two other patios
  • The last patio has not been worked on yet