Membrane work, June 6, 2026

Weather: 17°C, Showers, with afternoon sunny breaks
Workers onsite: Unknown

Work done today:

Unknown. I was away for most of the afternoon, but did not see any signs of activity. It is possible patio work may have been done that is not visible from the central courtyard.

Membrane work, June 5, 2026

Weather: 16°C, cloudy, some showers
Workers onsite: At least four

Work done today:

  • Additional work on applying sealant and membrane to some patios.
  • Membrane applied to the majority of emergency repair area.
  • Delivery of aeration mat, stacks in both emergency repair and Phase 1 areas.
  • Repair of sidewalk adjacent to emergency repair area. When the repairs have cured, this sidewalk will be treated with the same coating used on crosswalks to provide a seal.

Membrane work, June 4, 2026

Weather: 21°, partly sunny
Workers onsite: Unknown

Work onsite today:

I did not observe any workers onsite today. It’s possible they are awaiting delivery of the aeration (drainage) mat and root barrier, materials which will go over top of the membrane already in place.

I was also not onsite all day myself, so additional work on patios may have been done while I was away, particularly on the ones facing Brunette Avenue, which cannot be seen from the central courtyard.

Membrane work, June 3, 2026

Weather: 21°, cloudy
Workers onsite: Unknown

Today’s report is a little opaque because I did not see much!

Work done today:

  • Fencing around the Phase 1 area has been covered with mesh, to help keep debris and material from spreading out from the work area.
  • I am unsure if other work was done.

Membrane work, June 2, 2026

Weather: 29°, sunny
Workers onsite: At least 8

Work done today:

  • Further work on the membrane in the Phase 1 area near Building 244, including the upturns on patios facing the site.
  • Sealant applied in the emergency repair area between Building 240 and 244.
  • Material placed over the fencing of the emergency repair area to help minimize airborne debris and dust.

Membrane work, June 1, 2026

Weather: 26°, sunny
Workers onsite: At least 8

Work done today:

  • Sealant and membrane were applied to the Phase 1 area in front of the 244 building, bringing this section closer to completion.
  • More work was done on repairing and readying the patios in the emergency repair area.
  • Temporary fencing was erected at the southeast corner of the 244 building.
  • The fencing around the emergency repair area was pulled in, freeing up four parking stalls and allowing vehicle traffic to go all the way around the central courtyard.

The last two items were done as a result of being brought up by Council President Jeff.