Phase 2 membrane project, Day 66–October 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Additional extension of pavers in the parking lot adjacent to Building 244
  • Filter fabric placed alongside Building 240’s east edge in preparation for reinstatement of sidewalk
  • Trench drain ends were dug out for inspection. This is to prepare for its replacement or possible refurbishment. The holes were filled after the inspection was complete.

Phase 2 membrane project, Day 65–October 7, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 19°C, mostly sunny
Workers onsite: At least 6

Work done today:

  • Continued placement of pavers in the visitor parking lot adjacent to Building 244

Phase 2 membrane project, Day 64–October 6, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, mostly sunny
Workers onsite: At least 9

Work done today:

  • Blue Drop continued installing new irrigation piping
  • Additional drainage mat and wooden beams installed along perimeter of Buildings 240 and 244
  • More compacting of gravel throughout work area
  • Removal of old, more finely ground gravel from Phase 1 extension area. This will be replaced by the newer aggregate material approved by Strata Engineering.
  • A small section of pavers has been reinstalled in the parking lot adjacent to Building 244

Phase 2 membrane project, Day 63–October 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 19°C, mostly sunny
Workers onsite: At least six

Work done today:

  • More compacting of the gravel in all areas adjacent to Buildings 240 and 244
  • Installation of 4″x8″x24″ sections of bricks forming a transition between the parking lot and sidewalks alongside both Building 240 and 244. This is a new feature to help keep the sidewalk stable and prevent sinking/drifting.
  • More wooden beams placed, including some placed flush against patios to form a barrier to help stabilize the sidewalks
  • Drainage mat placed along perimeter of parking lot in more areas
New ventilation shaft installed.

Phase 2 membrane project, Day 61–October 2, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 17°C, cloudy, occasional drizzle
Workers onsite: At least 6

Work done today:

  • Further compacting of gravel
  • Laying of filter fabric adjacent to Building 244
  • Testing of a mock-up for the transition between parking lot and sidewalk by Building 244