Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 18°-22°C, mostly sunny
Workers onsite: At least 6
Work done over the past two days:
- Additional pavers install led near entrance of Building 244 and working toward the 240 building
- More dirt placed in the emergency repair area
- Gravel is being compacted in the Phase 1 extension
- A polymer joint compound is being poured over installed pavers, to help provide waterproofing by filling gaps between the pavers
Photos coming soon–I have not been able to get out recently until it is already dark.









