Phase 2 membrane project, Day 98–November 18, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 10°C, mostly sunny
Workers onsite: At least 6

Work done today:

  • More compacting of gravel/substrate around central courtyard
  • More pavers reinstated in the same area
  • Demolition of the Building 240 main entrance area, with removal of pavers and the stripping of membrane in progress

NOTE: The fire door has been left in an unlocked position so residents of Building 240 can more easily enter and exit the building while the main entrance is temporarily closed.

Phase 2 membrane project, Day 97–November 17, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, mostly sunny
Workers onsite: At least 6

Work done today:

  • Compacting of gravel/substrate around the central courtyard
  • Reinstatement of pavers in some of the central courtyard parking stalls

(No photos available for this day.)

Quay Pacific notice: New assigned strata manager for Copperstone

Effective immediately, a new strata property manager has been assigned to Copperstone, Jihad Faris. The email address for contacting the strata manager remains unchanged: manager.copperstone@quaypacific.com.

The previous manager, James Jamieson, has retired.

See PDF below for the official announcement.

Prostar notice: Copperstone entry notice – Building 240 entrance closed on Nov. 18, 2026

Prostar has issued the following notice that starting on Wednesday, November 18, 2026, the main entrance of the 240 building will be temporarily closed as the entrance area is stripped and new membrane is laid down. Prostar will provide an update on when the entrance will reopen.

Unlike Building 244, this will not be done in stages, but all at once.

Phase 2 membrane project, Day 96–November 16, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 12°C, clouds and some sun
Workers onsite: 6–8

Work done today:

  • More gravel/substrate was spread around the central courtyard; additional gravel was also delivered
  • Compacting of the substrate in the same area began
  • After an onsite meeting, the corners of the central courtyard were pulled in tighter, to reduce vehicles colliding with the Allan blocks
  • Blue Drop worked on the irrigation through the central courtyard, which will be routed more efficiently than before
  • Housekeeping saw a large volume of garbage/waste material removed from the site