Membrane work, June 24, 2026

Weather: 30°C, mostly sunny
Workers onsite: 2

Work done today:

  • Temporary path from the fire door adjacent to the 244 building entrance was completed in anticipation of the temporary closure of the building entrance starting tomorrow. That work has now been postponed until Monday, July 6, 2026. It is unclear how this path will affect work in the Phase 1 extension area over the next 11 days.
  • No other work was observed onsite, though there is a lot that can obviously be done, especially with good weather.
Temporary path from 244 fire door that will be used starting July 6, 2026.

Building 244 main entrance temporary closure postponed until Monday, July 6, 2026

What the title says. Apparently Prostar cannot do the work if there is precipitation. I guess this means if it showers on July 6 or on any other future start date they will literally never complete the project1.

Here’s the revised notice.

  1. Sarcasm alert, for those unaware. ↩︎

Membrane work, June 23, 2026

Weather: 32°C, sunny
Workers onsite: 2

Work done today:

  • Additional pavers for the sidewalk added to the emergency repair area.
  • Some metal flashing (trim) has been restored to some patios.
  • Patio railings were re-instated (see photos and notes on this below).

Building 244 entrance closure Thursday, June 25, 2026 (both notices)

Today, Quay Pacific prematurely sent out a notice regarding the temporary closure of the 244 building entrance. A short time later, a revised notice was sent out. I will be providing both notices below.

Also unlike Prostar, I’ll include a map of the entrances and exits of the 244 building.

Here’s the revised notice:

And here’s the original notice:

Here is a map showing the exits and entrances to the 244 building.

With the main entrance closed, you can exit and enter the 244 building as follows:

  • Exit only: Through the fire door immediately to the left of the main entrance. No key or fob required.
  • Exit only: Through the fire door at the east end of the hallway on the first floor. No key or fob required.
  • Exit and entrance: Through the door to the left of the underground parking entrance. This requires a fob for entry into the building, same as the main entrance.

Membrane work, June 22, 2026

Weather: 32°C, sunny
Workers onsite: At least 4

Work done today:

  • River stone/gravel was added to some of the emergency repair area.
  • Additional pavers/pedestals were placed on some patios.
  • Pavers were extended in the Phase 1 extension area in a way that doesn’t match the previous design–see photos below.

Membrane work, June 20, 2026

Weather: 23°C, sunny
Workers onsite: At least 4

Work done today:

  • Work today was focused on restoring pavers on patios in the emergency area. This work is nearly complete.