Phase 2 membrane project, Day 34–August 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21°C, cloudy, some sun
Workers onsite: At least four

Work done today:

  • Sealant applied to newly exposed concrete slab areas by Building 244
  • Membrane applied to one of the two above areas
  • Prostar has placed two sandwich boards noting no visitor parking

Phase 2 membrane project, Day 33–August 27, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21°C, cloudy, scattered showers
Workers onsite: At least two

Work done today:

  • Further scraping and cleaning of the concrete slab in front of Building 240
  • The porta-potty was moved from the central courtyard

Issues with mail delivery to Building 244

Council is aware of access issues affecting Building 244 for mail delivery. The mail carrier key is working with Building 240 and 248, but for some reason it has stopped working this past week in Building 244.

While the cause of the issue is investigated, please help out the mail carrier by letting her into the Building 244 lobby to deliver the mail. Mail delivery usually happens between 12–1 p.m. Monday through Friday.

Phase 2 membrane project, Day 32–August 26, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 25°C, mostly sunny
Workers onsite: At least four

Work done today:

  • Clearing of concrete slab adjacent to emergency repair area
  • Stripping of membrane from concrete slab next to Building 240

Phase 2 membrane project, Day 31–August 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 32°C, sun with smoke haze
Workers onsite: At least four

Work done today:

  • Continued clearing of new area in front of Building 240
  • Pavers restored to more Building 240 patios