Phase 2 membrane project, Day 63–October 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 19°C, mostly sunny
Workers onsite: At least six

Work done today:

  • More compacting of the gravel in all areas adjacent to Buildings 240 and 244
  • Installation of 4″x8″x24″ sections of bricks forming a transition between the parking lot and sidewalks alongside both Building 240 and 244. This is a new feature to help keep the sidewalk stable and prevent sinking/drifting.
  • More wooden beams placed, including some placed flush against patios to form a barrier to help stabilize the sidewalks
  • Drainage mat placed along perimeter of parking lot in more areas
New ventilation shaft installed.

Phase 2 membrane project, Day 61–October 2, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 17°C, cloudy, occasional drizzle
Workers onsite: At least 6

Work done today:

  • Further compacting of gravel
  • Laying of filter fabric adjacent to Building 244
  • Testing of a mock-up for the transition between parking lot and sidewalk by Building 244

Phase 2 membrane project, Day 60–October 1, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 16°C, cloudy, early showers
Workers onsite: At least 6

Work done today:

  • More compacting of the gravel, particularly adjacent to Building 240

Phase 2 membrane project, Day 59–September 29, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 15°C, cloudy, some showers
Workers onsite: At least 6

Work done today:

  • Further extension of aggregate (gravel) on drainage mat adjacent to Building 240
  • Additional layer and compacting of gravel adjacent to Building 244