Phase 1 Membrane Project, Day 131 (February 11, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, mostly sunny, some clouds

No work onsite today.

Fun Fact: Today marks six months since mobilization began on the membrane project, which started on August 11, 2025.

Phase 1 Membrane Project, Day 130 (February 10, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, mostly sunny

No work onsite today.

Cleaning the Allen Street staircase

Council Vice President Jeff has finished power-washing the stairs and walk leading to Allen Street, on the south side of the 244 building.

You can see how much dirt had built up over the years in this in-progress shot of the work:

And the same wall after cleaning was complete:

I don’t have a before shot of the stairs, but here’s how they looked after cleaning:

(Jeff does the power-washing on his own time and at his own expense, so it doesn’t take away from his duties as a member of Copperstone Council.)

Phase 1 Membrane Project, Day 129 (February 9, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, showers

No work onsite today.

The biweekly meeting was held onsite today with representatives from:

  • Prostar
  • Strata Engineering
  • Quay Pacific
  • Copperstone Council (represented by the Vice President)

Phase 1 Membrane Project, Day 127 (February 6, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, sun and cloud

No work onsite today.

Strata Engineering was onsite doing an inspection in the morning.