Building 244 main entrance is now temporarily closed, July 6, 2026

Prostar has now closed off the main entrance to the 244 building to complete the Phase 1 extension work on the membrane project. See the map below for how to enter and exit the building during the closure.

Note that there is no official estimate on how long the work will take, as Prostar was asked by Strata Council to provide an estimate and refused.

Given their usual efforts, I would estimate up to two weeks, perhaps longer if there are delays for unforeseen reasons.

We will keep you posted on the work here.

Membrane work, July 3, 2026

Weather: 22°C, sun and clouds
Workers onsite: At least five

Work done today:

  • River stone/gravel added in Phase 1 extension
  • Completion of reinstatement of pavers in Phase 1 extension
  • Additional placement of Allen blocks on planter adjacent to the 248 building
  • The pavers outside the fire door of the 240 building have been adjusted to allow the door to open properly

Membrane work, July 2, 2026

Weather: 15°C, showers and clouds
Workers onsite: At least five

Work done today:

  • Gravel added to top level of Allen blocks in planters in the Phase 1 area
  • Additional work on metal flashing through the emergency repair area
  • Additional housekeeping/cleaning in the emergency repair area

Membrane work, June 30, 2026

Weather: 20°C, mostly cloudy
Workers onsite: Two observed

Work done today:

  • Additional installation of metal flashing was done on the 240 and 244 buildings and patios in the emergency repair area
  • General cleaning of the emergency repair area was done