Phase 2 membrane project, Day 85–November 2, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Sealant applied to most of the remaining exposed concrete slab
  • Membrane laid down on a large portion of the concrete slab

Phase 2 membrane project, Day 84–October 31, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 13°C, mostly sunny
Workers onsite: At least 3

Work done today:

  • Remainder of exposed concrete slab has been ground/polished
  • Initial layer of sealant has been applied to a large portion of the area

Phase 2 membrane project, Day 83–October 30, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, cloudy, some light showers
Workers onsite: At least 6

Work done today:

  • Continued grinding/polishing of concrete slab to allow new membrane installation
  • Temporary shelter erected on completed area adjacent to Building 244 (I do not know its exact purpose)
  • Delivery of new membrane and sealant. This will be used to cover the last of the visitor parking lot.

Phase 2 membrane project, Day 83–October 29, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 10°C, cloudy, intermittent showers
Workers onsite: At least 3

Work done today:

  • Water mitigation to reduce water leaking into underground parking
  • Polishing of recently exposed concrete slab to prepare it for sealant and new membrane