Phase 2 membrane project, Day 55–September 24, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 16°C, mostly cloudy, showers in afternoon
Workers onsite: At least four

Work done today:

  • Cleaning bricks (pavers)
  • Area near patio closest to 244 entrance has had root barrier laid and material is being built up to help create a slope for better drainage

Phase 2 membrane project, Day 52–September 21, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, sunny
Workers onsite: None

No work done today.

Phase 2 membrane project, Day 50–September 18, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least 6

Work done today:

  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks