Phase 2 membrane project, Phase 2, Day 9–July 29, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23°C, sunny
Workers onsite: At least four

Work done today:

  • Kryton (concrete-like) material applied to cracks in concrete slab adjacent to Building 244
  • Initial sealant and membrane applied to some areas of the slab

Phase 2 membrane project, Day 8–July 28, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 22°C, mix of clouds and sun
Workers onsite: At least four

Work done today:

  • Further work on preparing the concrete slab in front of Building 244 for new membrane.
  • Sealant, membrane, and aeration (drainage) mats have arrived for the area.

Phase 2 membrane project, Day 7–July 27, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 22°C, mostly cloudy
Workers onsite: At least four

Work done today:

  • Concrete slab adjacent to Building 244 further stripped and polished

Phase 2 membrane project, Day 6–July 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 18°C, mostly cloudy
Workers onsite: At least five

Work done today:

  • Completion of stripping membrane in front of Building 244
  • Concrete slab in same area polished in preparation for new membrane
  • Area now connects to the work in the emergency repair area

Phase 2 membrane project, Day 5–July 24, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 27°C, sunny
Workers onsite: At least five

Work done today:

  • Stripping of membrane and polishing of concrete slab in area of visitor parking in front of Building 244 began

Phase 2 membrane project, Day 4–July 23, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 26°C, mostly sunny
Workers onsite: At least five

Work done today:

  • Completion of removal of pavers in area of parking lot adjacent to 244 building
  • Removal of sand from the same area (new sand is used due to contamination and other issues with existing sand)
NOTE: The workers were here well past their usual time. I don't have insider information, but I believe what happened is they needed to have the (very large) amount of sand removed tonight so they could begin stripping the old membrane tomorrow and the dump truck arrived late for reasons unknown.