Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: December 2026 Primary contractor: Prostar https://prostar.ca/
Weather: 23°C, sunny Workers onsite: At least four
Work done today:
Kryton (concrete-like) material applied to cracks in concrete slab adjacent to Building 244
Initial sealant and membrane applied to some areas of the slab
Area showing sealant (base layer), with some membrane installed farther up.Newly-installed membrane on the far left and building edge, sealant showing to the right.No membrane has been applied here because the membrane upturn at the base of the building has not been done yet (a completed upturn can be seen to the right of the area covered with sealant).
Project Mobilization Date: July 20, 2026 Work Start Date: May 4, 2026 (for emergency repairs) Expected completion: December 2026 Primary contractor: Prostar https://prostar.ca/
Weather: 26°C, mostly sunny Workers onsite: At least five
Work done today:
Completion of removal of pavers in area of parking lot adjacent to 244 building
Removal of sand from the same area (new sand is used due to contamination and other issues with existing sand)
Are stripped of pavers and most sand. Water is from a shower that passed over shortly before the shot was taken.Similar shot, but looking to the west.
NOTE: The workers were here well past their usual time. I don't have insider information, but I believe what happened is they needed to have the (very large) amount of sand removed tonight so they could begin stripping the old membrane tomorrow and the dump truck arrived late for reasons unknown.