Council released the following membrane and council reports on September 29, 2026:
Phase 2 membrane project, Day 60–October 1, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 16°C, cloudy, early showers
Workers onsite: At least 6
Work done today:
- More compacting of the gravel, particularly adjacent to Building 240

Phase 2 membrane project, Day 59–September 29, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 15°C, cloudy, some showers
Workers onsite: At least 6
Work done today:
- Further extension of aggregate (gravel) on drainage mat adjacent to Building 240
- Additional layer and compacting of gravel adjacent to Building 244



Phase 2 membrane project, Day 58–September 28, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 17°C, cloudy, late afternoon showers
Workers onsite: At least 6
Work done today:
- Continued spreading and compacting of gravel aggregate adjacent to Building 244

Phase 2 membrane project, Day 57–September 26, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 17°C, partly sunny
Workers onsite: At least 8
Work done today:
- More aggregate (sand) has been spread over the drainage mat adjacent to Building 244



Phase 2 membrane project, Day 56–September 25, 2026
Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 14°C, showers and clouds
Workers onsite: At least six
Work done today:
- Delivery of aggregate material (sand) to the site
- Aggregate (sand) spread over existing drainage mat adjacent to Building 244
- Reinstatement of wooden beans near corner of main entrance of Building 244


