Phase 2 membrane project, Day 57–September 26, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 17°C, partly sunny
Workers onsite: At least 8

Work done today:

  • More aggregate (sand) has been spread over the drainage mat adjacent to Building 244

Phase 2 membrane project, Day 56–September 25, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 14°C, showers and clouds
Workers onsite: At least six

Work done today:

  • Delivery of aggregate material (sand) to the site
  • Aggregate (sand) spread over existing drainage mat adjacent to Building 244
  • Reinstatement of wooden beans near corner of main entrance of Building 244

Phase 2 membrane project, Day 55–September 24, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 16°C, mostly cloudy, showers in afternoon
Workers onsite: At least four

Work done today:

  • Cleaning bricks (pavers)
  • Area near patio closest to 244 entrance has had root barrier laid and material is being built up to help create a slope for better drainage

Phase 2 membrane project, Day 52–September 21, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, sunny
Workers onsite: None

No work done today.