Membrane work, June 30, 2026

Weather: 20°C, mostly cloudy
Workers onsite: Two observed

Work done today:

  • Additional installation of metal flashing was done on the 240 and 244 buildings and patios in the emergency repair area
  • General cleaning of the emergency repair area was done

Membrane work, June 29, 2026

Weather: 21°C, mostly cloudy
Workers onsite: At least two

Work done today:

  • Work was done on establishing pedestrian access through the emergency repair area (see photos below)
  • Additional work was done to complete pedestrian access in the Phase 1 extension area and to the stairs leading to the hospital lane.
  • General housekeeping (clean-up) was done, particularly in the emergency repair area
  • The biweekly meeting took place onsite with the following parties attending:
    • Strata Engineering
    • Prostar
    • Copperstone Council (represented by the President)
    • Quay Pacific did not have anyone in attendance

At the biweekly meeting, Prostar stated the pedestrian access noted above would be ready by the end of this week (Friday, July 3). From my observations, the access through the emergency repair area appears to be ready and all barriers/fencing have been removed.

There is also a reasonable expectation that the City of New Westminster will finally grant the permit for Phase 2 within the next few weeks.

Membrane work, June 25, 2026

Weather: 20°C, cloudy
Workers onsite: At least 2

Work done today:

  • Soil placed in the Phase 1 extension, adjacent to the wooden beams, with additional soil placed into the planter adjacent to the 244 building.
  • Bridge placed in emergency repair area, possibly to allow foot traffic through as remainder of the area is worked on.
  • Flashing is being cut and put back into the base of the 244 building in the emergency repair area.