Phase 2 membrane project, Day 3–July 22, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 33°C, sunny
Workers onsite: At least five

Work done today:

  • Two of the four Building 244 patios have had membrane applied
  • More pavers have been removed from the parking lot adjacent to Building 244

Phase 2 membrane project, Day 2–July 21, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 33°C, sunny
Workers onsite: At least four

Work done today:

  • Additional work on the Building 244 patios facing the visitor parking
  • A section of pavers was removed from the parking lot in front of the patios
  • Plywood planking was removed from the temporary ramp that had been installed at the Building 244 entrance

Phase 2 membrane project, Day 1 – July 20, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 31°C, mostly sunny
Workers onsite: 6–8, varying at times

Work done today:

  • Entire south side of visitor parking lot fenced off
  • Pavers removed from south sidewalk adjacent to Building 244
  • Start of demolition of four patios in Building 244 for membrane replacement
  • Allan blocks removed from remaining planter outside Building 244
  • Two down spouts fitted to Building 240 in the emergency repair area

A few observations:

  • The majority of the closed-off parking area is not being used and the loop around is again cut off. This severely restricts the number of parking spaces and may hinder access by emergency vehicles.
  • I have already observed people parking in any free space.
  • No work in the Phase 1 extension or emergency repair area (except the down spouts being attached as noted above). Unclear when these areas will be done, with the project now expanding into Stage 3.

Phase 2 of the membrane project officially starts today, July 20, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

The City of New Westminster has finally granted the permit and today is the day when Phase 2 of the membrane replacement project officially gets underway.

I am not aware of any explanation from Prostar or Strata Engineering on why no work was done over the past week in either the Phase 1 extension area or the emergency repair area.

The notice provided to owners by Prostar outlining “Stage 3” is below.