Temporary walkway closure–August 5, 6 or 7th, 2026–you pick!

This notice was released by Prostar today:

  • Actual closure started on August 5
  • Notice to owners sent August 7, but dated August 6

Speaking of updates, Prostar has had people onsite and working since May 4, 2026. Here is an update on what has been finished in that 3+ month period:

  • The Phase 1 extension is incomplete
  • The emergency area is incomplete
  • The Stage 3 area is incomplete
  • The patios are incomplete

Bonus:

  • The partial restoration of pavers in front of Building 244 is so out of alignment you get this:

Phase 2 membrane project, Day 16–August 7, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 28°C, sunny
Workers onsite: At least three

Work done today:

  • Two of the Building 240 patios had membrane applied
  • Sealant was applied to two other patios
  • The last patio has not been worked on yet

Enterphone installation complete, August 7, 2026

Omicron started a bit late, but finished installing the new enterphones in all three buildings right on schedule.

A few items to note:

  • Programming on all enterphones should be complete and matches what was in the system before
  • Unit numbers are not shown, as before, just buzzer codes
  • You can now buzz a unit by just tapping on the name, no need to enter the buzzer code
  • On the other end, a recording will play giving the owner/resident options. To buzz someone in, you now press the asterisk key (*), not the number zero (0)
  • I do not know what “PIN unlock” does

I’m assuming Omicron will provide more information on the operation of the units. I will post any new information if I get it.

Phase 2 membrane project, Day 15–August 6, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 29°C, sunny with some smoke haze
Workers onsite: At least three

Work done today:

  • Additional work on some of the newly exposed patios at Building 240

Minor delay in Enterphone replacement–work today on Building 240 (Aug. 6, 2026)

UPDATE: The 240 building enterphone replacement is complete, see photo below.

It has a light!

The previously announced schedule for Enterphone replacement was:

  • Building 240: Aug. 5
  • Building 244: Aug. 6
  • Building 248: Aug. 7

However, Omicron was not onsite yesterday. I can confirm the 240 building Enterphone is being replaced as I type this, so they appear to be one day behind schedule. I’m not sure how this will affect Buildings 244 and 248.

I’ll update this post if I get more information.

NOTE: Fobs will continue to work normally while the Enterphone is being replaced, so entering a building will work as normal for residents. Each Enterphone is estimated to be out of service for about eight hours while being replaced.

Phase 2 membrane project, Day 14–August 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 29°C, sunny with smoke haze
Workers onsite: At least seven

Work done today:

  • Completion of application of sealant and membrane in the recently cleared concrete slab adjacent to Building 244.
  • Closure of access to Allen Street, except via fire door in Building 240, to allow for further membrane installation.

Notes:

  • The closure of pedestrian access to Allen Street is expected to last one week, per Prostar. As the closure and notice of the closure were given the same day, it was not possible to get advance word out to owners and other residents.