Minor delay in Enterphone replacement–work today on Building 240 (Aug. 6, 2026)

The previously announced schedule for Enterphone replacement was:

  • Building 240: Aug. 5
  • Building 244: Aug. 6
  • Building 248: Aug. 7

However, Omicron was not onsite yesterday. I can confirm the 240 building Enterphone is being replaced as I type this, so they appear to be one day behind schedule. I’m not sure how this will affect Buildings 244 and 248.

I’ll update this post if I get more information.

NOTE: Fobs will continue to work normally while the Enterphone is being replaced, so entering a building will work as normal for residents. Each Enterphone is estimated to be out of service for about eight hours while being replaced.

Phase 2 membrane project, Day 14–August 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 29°C, sunny with smoke haze
Workers onsite: At least seven

Work done today:

  • Completion of application of sealant and membrane in the recently cleared concrete slab adjacent to Building 244.
  • Closure of access to Allen Street, except via fire door in Building 240, to allow for further membrane installation.

Notes:

  • The closure of pedestrian access to Allen Street is expected to last one week, per Prostar. As the closure and notice of the closure were given the same day, it was not possible to get advance word out to owners and other residents.

Phase 2 membrane project, Day 13–August 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 29°C, sunny with smoke haze
Workers onsite: At least seven

Work done today:

  • Sealant applied to most of the newly exposed concrete slab in the visitor parking adjacent to Building 244
  • Membrane installation continuing in the same general area
  • Initial work on the next set of patios, including removal of some Hardie planking

Phase 2 membrane project, Day 12–August 1, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23°C, cloudy, some sun, early morning showers
Workers onsite: At least three

Work done today:

  • Further stripping and cleaning of the exposed concrete slab in the parking lot

Phase 2 membrane project, Day 11–July 31, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 27°C, sunny
Workers onsite: At least five

Work done today:

  • Membrane applied to most of the newly cleared concrete slab in front of Building 244.
  • Upturns (membrane) applied to remainder of the base along the 244 building.
  • Further demolition of the visitor parking, now encompassing about half of the parking lot.

Phase 2 membrane project, Day 10–July 30, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 23°C, sunny
Workers onsite: At least four

Work done today:

  • Further expansion of the Stage 3 area, demolition of more of the south side of the visitor parking lot adjacent to the 244 building