Phase 2 membrane project, Day 46–September 14, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 18°C, cloudy
Workers onsite: At least 6

Work done today:

  • Cleaned bricks (pavers)
  • A few patio drains appear to have been cleaned, or at least pavers were removed to potentially clean them

Phase 2 membrane project, Day 45–September 12, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 22°C, partly sunny
Workers onsite: At least 3

Work done today:

  • You guessed it, cleaning pavers (bricks)!
A Brief FAQ

Q: Do you know why the workers have only been cleaning bricks the last four days?
A: I do not know the reason, though I have some thoughts on possible reasons.

Q: What are your thoughts?
A: It may be related to communication between Strata Engineering (company overseeing the project) and Prostar (company doing the work) on certain aspects of the project moving forward related to materials, work already done, possible deficiencies and more.

Q: Do you know when full work will resume?
A: I do not. My best guess is we will see more normal work activity resume during the week of September 14–19th.

Q: Will this delay the completion of the project?
A: I know this: That council wants the project complete by December 2026, and that Prostar wants to extend the project well into 2027. How this turns out, I do not know.

The site as of September 12, 2026:

Phase 2 membrane project, Day 44–September 11, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, partly sunny
Workers onsite: 6

Work done today:

  • Cleaning pavers (bricks). Yes, again.

Phase 2 membrane project, Day 43–September 10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, partly sunny
Workers onsite: 6

Work done today:

  • Pavers (bricks) cleaned
  • No other work observed

Phase 2 membrane project, Day 42–September 9, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, partly cloudy
Workers onsite: 6

Work done today:

  • Pavers (bricks) cleaned
  • No other work observed

(No photos today.)

Phase 2 membrane project, Day 41–September 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, cloudy, some clearing
Workers onsite: 6

Work done today:

  • Additional flashing applied to Building 244
  • More work on planter boxes at Building 244 entrance