Temporary walkway closure–August 5, 6 or 7th, 2026–you pick!

This notice was released by Prostar today:

  • Actual closure started on August 5
  • Notice to owners sent August 7, but dated August 6

Speaking of updates, Prostar has had people onsite and working since May 4, 2026. Here is an update on what has been finished in that 3+ month period:

  • The Phase 1 extension is incomplete
  • The emergency area is incomplete
  • The Stage 3 area is incomplete
  • The patios are incomplete

Bonus:

  • The partial restoration of pavers in front of Building 244 is so out of alignment you get this:

Phase 2 membrane project, Day 16–August 7, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 28°C, sunny
Workers onsite: At least three

Work done today:

  • Two of the Building 240 patios had membrane applied
  • Sealant was applied to two other patios
  • The last patio has not been worked on yet

Enterphone installation complete, August 7, 2026

Omicron started a bit late, but finished installing the new enterphones in all three buildings right on schedule.

A few items to note:

  • Programming on all enterphones should be complete and matches what was in the system before
  • Unit numbers are not shown, as before, just buzzer codes
  • You can now buzz a unit by just tapping on the name, no need to enter the buzzer code
  • On the other end, a recording will play giving the owner/resident options. To buzz someone in, you now press the asterisk key (*), not the number zero (0)
  • I do not know what “PIN unlock” does

I’m assuming Omicron will provide more information on the operation of the units. I will post any new information if I get it.

Phase 2 membrane project, Day 15–August 6, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 29°C, sunny with some smoke haze
Workers onsite: At least three

Work done today:

  • Additional work on some of the newly exposed patios at Building 240

Minor delay in Enterphone replacement–work today on Building 240 (Aug. 6, 2026)

UPDATE: The 240 building enterphone replacement is complete, see photo below.

It has a light!

The previously announced schedule for Enterphone replacement was:

  • Building 240: Aug. 5
  • Building 244: Aug. 6
  • Building 248: Aug. 7

However, Omicron was not onsite yesterday. I can confirm the 240 building Enterphone is being replaced as I type this, so they appear to be one day behind schedule. I’m not sure how this will affect Buildings 244 and 248.

I’ll update this post if I get more information.

NOTE: Fobs will continue to work normally while the Enterphone is being replaced, so entering a building will work as normal for residents. Each Enterphone is estimated to be out of service for about eight hours while being replaced.