Minor site update complete

I’ve done some minor touch-up work on the site, rounding off corners and updating fonts and logos for a cleaner, hopefully more modern look.

None of the site functionality has changed. The forum is still based on a WordPress plugin, and I continue to look for better options. In the meantime, feel free to register and post. Right now the forum is a community of one–me! And I don’t need an entire dedicated forum to talk to myself. 😛

Cleaning around the main sign and sidewalks

Jeff power-washed the stone cladding around the main Copperstone sign again. This was last done in September, showing how quickly moss can grow back on an untreated surface. He also began washing down the nearby sidewalk, which has taken to growing a bit of moss as well.

Here’s a shot showing a section of sidewalk after power-washing, with an untouched section farther up.

The stone cladding around the Copperstone sign is moss-free–again!

Phase 1 Membrane Project, Day 133 (February 13, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, rain and clouds

Work done today:

  • The excess fabric was trimmed along the top edge of the concrete curb at the base of the retaining wall behind the 244 building.
  • The area in the first tier of the retaining wall to the right of the ventilation shaft was tidied up and soil was used to fill the space. The soil was taken from further down the first tier.
  • It appears the exposed electrical cable on the pavers was placed under the pavers.
  • Soil was also taken from the pile at the front of the site, but I could not determine where it went.
  • Workers onsite: Two.

I believe the spout in the photo above is the one seen in this photo I took yesterday, just visible near the small flag near the centre of the photo:

Phase 1 Membrane Project, Day 132 (February 12, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, cloudy

No work onsite today.

I decided to take a walk along the newly-reopened path leading to the stairs and found a few things that stood out–not in a good way.

Phase 1 Membrane Project, Day 131 (February 11, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, mostly sunny, some clouds

No work onsite today.

Fun Fact: Today marks six months since mobilization began on the membrane project, which started on August 11, 2025.