Phase 2 membrane project, Day 73–October 17, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 18°C, mostly sunny
Workers onsite: At least 6

Work done today:

  • Paver installation extended further toward the entrance of Building 240
  • More pavers installed in the Phase 1 extension adjacent to Building 244
  • Some initial work on the sidewalk alongside the east side of Building 240

I noted numerous cases of misalignment across the site with regard to pavers, the new concrete curbs, wooden beams and planters. Since I don’t know if/how these issues will be fixed, I’ve chosen not to include the shots I took documenting them. But I do have shots!

Phase 2 membrane project, Day 71 and 72–October 15 and 16, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 18°-22°C, mostly sunny
Workers onsite: At least 6

Work done over the past two days:

  • Additional pavers install led near entrance of Building 244 and working toward the 240 building
  • More dirt placed in the emergency repair area
  • Gravel is being compacted in the Phase 1 extension
  • A polymer joint compound is being poured over installed pavers, to help provide waterproofing by filling gaps between the pavers

Photos coming soon–I have not been able to get out recently until it is already dark.

Phase 2 membrane project, Day 70–October 14, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 18°C, cloudy with showers early in morning, then clearing
Workers onsite: At least 6

Work done today:

  • Further extension of pavers in parking lot around the planter by the emergency repair area
  • Initial placement of pavers are being installed on Building 244 sidewalk along south side
  • Soil has been brought in and distributed in most areas where grass will be located

Phase 2 membrane project, Day 69–October 13, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: Around 16°C, partly sunny
Workers onsite: At least 3

Work done today:

  • Phase 1 extension removal of old gravel complete, new gravel is being put in place
  • More compacting of area adjacent to Building 240
  • More work on leveling and compacting fine gravel for sidewalk adjacent to Building 244

Phase 2 membrane project, Day 67 and 68–October 9/10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: Around 13–15°C, mostly sunny
Workers onsite: At least 3

I’ve been busy the past few days so I’m combining the work done on Friday and Saturday into one post.

Work done:

  • Some more pavers installed in the parking lot
  • Additional compacting of gravel in the area in front of the 240 building (Saturday)
  • Some minor housekeeping (cleaning, organization)

It’s possible other work may have been done, but I did not observe anything specific.

Phase 2 membrane project, Day 66–October 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Additional extension of pavers in the parking lot adjacent to Building 244
  • Filter fabric placed alongside Building 240’s east edge in preparation for reinstatement of sidewalk
  • Trench drain ends were dug out for inspection. This is to prepare for its replacement or possible refurbishment. The holes were filled after the inspection was complete.