Phase 2 membrane project, Day 53–September 22, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 20°C, mostly sunny
Workers onsite: None

No work onsite today.

I have learned that approval of the latest changes in labour and material are the official reason no work has been done on the project (other than cleaning bricks) since September 9th. That list of changes was only delivered yesterday (September 21).

I leave it as an exercise for the reader on whether any other work could have been done between September 9th and now.

Phase 2 membrane project, Day 52–September 21, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, sunny
Workers onsite: None

No work done today.

Phase 2 membrane project, Day 50–September 18, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least 6

Work done today:

  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks
  • Cleaning bricks

Phase 2 membrane project, Day 49–September 17, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 23°C, sunny
Workers onsite: At least 6

Work done today:

  • Cleaning bricks.
  • Blue Drop (irrigation) came by and placed upright sprinkler heads in the three planter boxes that have been partially reassembled.

Phase 2 membrane project, Day 48–September 16, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 25°C, sunny
Workers onsite: At least 6

Work done today:

  • Bricks (pavers) cleaned (sixth day in a row)
  • Initial work on cutting down and removing the three trees in the central courtyard