Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 18°C, mostly sunny
Workers onsite: At least 6
Work done today:
- Paver installation extended further toward the entrance of Building 240
- More pavers installed in the Phase 1 extension adjacent to Building 244
- Some initial work on the sidewalk alongside the east side of Building 240


I noted numerous cases of misalignment across the site with regard to pavers, the new concrete curbs, wooden beams and planters. Since I don’t know if/how these issues will be fixed, I’ve chosen not to include the shots I took documenting them. But I do have shots!








