Phase 2 membrane project, Day 89–November 6, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 12°C, rain, at times heavy
Workers onsite: At least 4

Work done today:

  • Cleaning pavers (bricks)
  • Some minor housekeeping

Phase 2 membrane project, Day 88–November 5, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, mostly cloudy, intermittent showers
Workers onsite: At least 8

Work done today:

  • Membrane applied around base of ventilation shed in central courtyard
  • Waterproofing material applied around base of fire hydrant
  • More second layer of membrane installed
  • Potential spots for new drains highlighted
  • Deficiencies in the membrane highlighted for repair and inspection

Phase 2 membrane project, Day 87–November 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 12°C, mostly cloudy
Workers onsite: At least 8

Work done today:

  • Continued work on applying second layer of membrane to area near to Building 240

(No photos for this day.)

Phase 2 membrane project, Day 86–November 3, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 13°C, partly sunny
Workers onsite: At least 8

Work done today:

  • Near completion of first layer of membrane installed over recently exposed concrete slab

Phase 2 membrane project, Day 85–November 2, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 11°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Sealant applied to most of the remaining exposed concrete slab
  • Membrane laid down on a large portion of the concrete slab